Recent Industrial Electrical & Instrumentation Projects completed:
| GPA Berth 4 Enhancement Project E&I |
GPA |
$ 2,300,000.00 |
| Geraldton Bitumen Plant reassembly & commissioning |
Downer |
$ 115,000.00 |
| Mogensen Screen Project |
Iluka |
$ 520,000.00 |
| Lumps Crusher Project E&I |
Iluka |
$ 300,000.00 |
| ROC Oil Process Plant E&I |
Matricon |
$ 950,000.00 |
| Major Maintenance Outage, Kiln rebuild |
Iluka |
$ 400,000.00 |
Commercial Projects have included light and power, data and communications, nurse call systems, back up generator systems, Mechanical Services electrical. Recent Commercial Electrical Projects completed:
| Morawa/ Perenjori Hospital |
Cooper & Oxley |
$ 1,287,370.00 |
| John Willcock College Geraldton |
SJ Higgins |
$ 640,000.00 |
| Kalbarri District High School |
Broad Construction |
$ 770,021.00 |
| Burrup Fertilizer Project Service Buildings Karratha |
Wylie & Skene |
$ 465,291.00 |
| Nazareth House Retirement Home Upgrade Geraldton |
Crothers Construction |
$ 947,033.00 |
Infrastructure Projects have included installation of LV, HV and street lighting to new subdivisions and street lighting projects. Recent Infrastructure Projects completed:
| Retirement Home Village (less houses) Geraldton |
Arcadia Group |
$ 750,000.00 |
| Hailer Satellite Comms Project Geraldton |
RG Systems |
$ 380,000.00 |
| Parkfalls Stage 7 UDS White Peak |
Geraldton Paving Co |
$ 480,000.00 |
| Capital Hill UDS Kalbarri |
Central Earthmoving |
$ 1,200,000.00 |
| Rhodes Ridge Camp Upgrade Pilbara |
Rio Tinto |
$ 370,000.00 |
| NWCH Street Light Upgrade Geraldton |
Main Roads Dept |
$ 230,000.00 |
| Southern Corridor Stage 1 Geraldton |
Thiess |
$ 1,400,000.00 |
| Seacrest Stages 8 & 9 UDS Geraldton |
Central Earthmoving |
$ 760,000.00 |
 |
| “Geraldton Electrical Co’s skills in submitting tenders and price negotiation, and then applying the necessary attention to detail required for contractual and technical documentation, as well as project management, was evident during the Geraldton Port Berth 5 project. There is no doubt this a professional company with the management structures in place to handle large scale projects.” Robert Combs, Maunsell AECOM Consulting Engineers |
 |
|

 |